NCC 2025 in Queensland: what changes on 1 May 2027 and what does not

In Queensland, NCC 2022 remains in force until 30 April 2027 and NCC 2025 has legal effect from 1 May 2027. The Australian Building Codes Board published NCC 2025 on 1 May 2026, but the Queensland Government delayed its start. Projects being designed now should confirm with their building certifier which edition will apply when the building application is made.

Procurement · 21 November 2026

The dates

The National Construction Code is published by the Australian Building Codes Board, and each state decides when a new edition takes effect. NCC 2025 was published on 1 May 2026. Queensland chose a later start, and the code's own Queensland schedule states that all NCC 2022 provisions remain in force in Queensland until 30 April 2027 and that NCC 2025 is adopted and has legal effect on 1 May 2027.

Business Queensland, the QBCC and the ABCB's adoption table all give the same date. Queensland Government building and plumbing newsflashes 637 (19 March 2026) and 638 (1 May 2026) announced and confirmed the delay.

What does not change before 1 May 2027

Until that date, building work in Queensland is assessed against NCC 2022 together with the Queensland Development Code and the state's variations. Design drawings, certifications and specifications prepared now should reference NCC 2022 unless the certifier has confirmed that NCC 2025 will apply to the application.

Queensland-specific instruments such as QDC MP 1.4 (building over or near relevant infrastructure) and QDC MP 3.4 (swimming pool barriers) sit alongside the NCC and are not replaced by the change of edition. The requirement that professional engineering services in or for Queensland are carried out by, or under the direct supervision of, a practising RPEQ is set by the Professional Engineers Act 2002 and is not affected by the NCC edition.

Which edition applies to your project

Projects that straddle 1 May 2027 are where the questions arise. Which edition applies depends on when the building development application is made and on any transitional arrangements the Queensland Government publishes. The building certifier is the person who decides this for a specific application, so raise it at the start of design rather than at lodgement.

Practical cases to discuss with the certifier early:

  • Projects in design now that will not lodge for building approval until mid-2027
  • Staged developments where later stages lodge separate applications after 1 May 2027
  • Design and construct tenders where the design is finalised after contract award
  • Amendments to an existing approval made after 1 May 2027

What does change

From 1 May 2027 the NCC 2025 provisions become the mandatory minimum in Queensland for work assessed under that edition. The ABCB publishes the full code and supporting material free online, and it is the authoritative place to check how a particular provision has changed between editions.

This article does not summarise the technical changes clause by clause. The changes that matter depend on the building class and the systems involved, and a short summary can mislead. For a given project, the architect, building certifier and each engineering discipline should compare the provisions that affect their own scope.

How to plan around the change

For structural engineering, much of the design work is governed by Australian Standards referenced by the NCC, such as the loading, concrete and steel standards. A change of NCC edition can change which edition of a referenced standard applies, so the engineer should confirm the referenced documents for the project's edition before finalising calculations.

Clients can reduce the risk in three steps. Ask the certifier which edition they expect to apply, and record the answer in the project brief. Ask each consultant to state the NCC edition on their drawings and certificates. Where a project is likely to straddle the date, ask the design team to identify provisions that differ between editions early, so any cost is known before tender rather than discovered at approval.

What it means for common project types

Houses, extensions and pools usually move from design to building approval within a few months. A project in design now will most likely be approved under NCC 2022, but a homeowner who pauses for a year may find the application assessed under NCC 2025. If a project is on hold, note the edition on the drawings so the certifier and designer can check it when work resumes.

Commercial and multi-residential projects have longer design periods and often lodge in stages. These are the projects most likely to straddle the change, and the most exposed to redesign cost if the edition is discovered late. Settle the question at the design brief stage and record it in each consultant's scope.

Refurbishments and changes of use of existing buildings raise a separate question: how far the new work, and sometimes the existing building, must be upgraded to current provisions. The certifier decides this under the Queensland building assessment framework, and the answer can differ between editions, so it belongs in early advice.

Aquatic projects involve several layers at once. The pool structure, the barrier under QDC MP 3.4 and, for public or shared pools, a separate public swimming pool approval are assessed against different instruments, so each needs its own check against the timing.

Keeping up to date

Adoption dates can change, as this delay shows. Before relying on the dates above for a contract or programme, check the Business Queensland page on delayed adoption of NCC 2025 and the QBCC's NCC guidance. This article was last checked against those sources on 21 November 2026.

General information for Queensland projects, not advice for a specific site. Written by Coreline Engineering; engineering for a project is carried out or supervised by Mustafa Koc, RPEQ 35981.

Sources

Have a project that needs engineering input?

Tell us what you are building or assessing, where it is and what drawings or reports you already have. We will come back with questions, a scope and a fee.

Registered engineer
Mustafa Koc, RPEQ 35981 (Civil)
Add company, role and timing (optional)

We use these details only to respond to your enquiry. See our privacy policy. Please do not attach or paste plans here; we will ask for them by email once we have spoken.

Call 1300 924 666Discuss your project