Why it matters on small blocks
Backyards in South East Queensland are getting smaller while pools are not. A typical infill pool sits a metre or two from the house, a sleeper retaining wall or the neighbour's fence. Excavating 1.5 to 2 m deep beside a footing removes the soil that was holding it up sideways, and the footing can settle or slide into the hole.
The load influence line is the tool engineers use to decide whether a proposed excavation is clear of existing footings, and what to do when it is not.
How the line is drawn
Start at the underside edge of the existing footing nearest the pool. Draw a line down and away from the footing toward the pool at an angle measured from the horizontal. Soil below and behind that line is helping to support the footing. The pool excavation, including its base and any over-excavation for drainage, should stay above the line.
Engineers commonly use angles that reflect how well the ground holds a slope. A frequently used general guide is about 30 degrees for sand, 45 degrees for clay and 60 degrees for rock, measured from the horizontal. Looser or wetter ground can need a flatter line, and the geotechnical report for the site takes precedence over any rule of thumb.
Worked example in words
Picture a house footing whose base is 500 mm below ground, with the pool wall planned 1.5 m from the footing edge, on clay. A 45 degree line from the footing base drops one metre for every metre it travels sideways, so at the pool wall it is 1.5 m below the footing base, or about 2 m below ground. A pool 1.8 m deep at that wall would stay above the line. The same pool on sand, using a 30 degree line, would cut below it, because the line drops less steeply.
The example is illustrative. Real checks use measured footing depths, the actual pool profile and the site's soil report.
When the excavation crosses the line
There are four usual responses. Move the pool or reduce its depth near the footing. Underpin the existing footing so its base sits below the excavation level, with the underpinning designed and certified by an engineer. Design the pool wall itself as a retaining structure that holds up the ground behind it, with the excavation shored during construction. Or support the excavation temporarily with shoring while the shell is built and backfilled.
Underpinning design is a separate engineering task from the pool shell. Pool drawings often state that underpinning is outside the scope of the pool design and must be designed, certified and installed before the pool is excavated. The pool builder and the inspecting officer should confirm this has happened before digging starts.
Retaining walls and boundaries
A sleeper or block retaining wall near a pool behaves like a footing carrying the soil it retains. Its footing or post holes have their own influence line, and the wall's stability depends on the soil in front of it. Excavating that soil for a pool can tip the wall over. The same check applies, and the answer may be to rebuild the wall as part of the pool works.
Boundary fences and the neighbour's structures matter for a further reason: damage to them is a dispute with someone who did not agree to the work. Recording the condition of neighbouring structures before excavation, with dated photos, is a sensible precaution.
Sewers, stormwater and water mains
Underground pipes have a zone of influence too. In Queensland, building work near sewers, water mains and stormwater drains belonging to a service provider is regulated by QDC MP 1.4. Business Queensland lists the distances beyond which MP 1.4 does not apply, including 3 m for Class 1 and 10 structures, and an assessment of the zone of influence where a pool is closer. Some providers, such as the City of Gold Coast, also require consent for any work inside their easements.
Information the engineer needs
To check a pool against nearby footings, the engineer needs:
- A site plan showing the pool, house, retaining walls, fences and any sewer, with dimensions
- Pool depths along its length, including spa and deep end
- Depth and type of nearby footings, confirmed on site where drawings do not exist
- The soil test or geotechnical report
- Any existing cracking or movement in nearby structures
On site
Most pool drawings instruct the builder to confirm the existing foundations before construction and to stop and contact the engineer if a footing encroaches on the influence line. Following that instruction prevents most excavation damage. If the house footing turns out deeper or shallower than assumed, the check is redone with the real dimensions before excavation continues.
Weather matters as well. A pool excavation left open through heavy rain softens clay and can wash sand out from under nearby footings. Programming excavation, steel fixing and the shell pour close together, and keeping surface water out of the hole, reduces the time the neighbouring ground is unsupported.